As the development of electric vehicles, governments encourage entrepreneurs to
invest and construct EV Charger station .Before investment , It is necessary to
understand the explicit and implicit cost of commercial EV charging stations. There
is there type of ev charger : level 1 , level 2 ,level 3 . People always use level 3 for
commercial , and sometimes use level 2 . Level 1 almost not use for commercial.
Therefore let’s analyze the cost of level 2and level 3 ev charger as Commercial .
Explicit & Implicit Cost
1.Implicit Cost is not directly billed & always to be ignored ,it is hard to measure.
(1)Opportunity Cost . It’s a potential revenue which generates by investment for
alternative purposes.
(2)Downtime Cost. It’s lost revenue during the period of installation and maintenance.
(3)Outdated technological . As rapid development of charging technology, the
equipment possible become outdated and need update the technology.
2.Explicit Cost is direct expense which includes purchase cost, installation cost,
operation cost & electricity cost.They are easy to quantifiable.
Different country different standard different cost ,take USA as example .
(1)Purchasing Cost (there is big different between different power & brand)
Level 2 Charger: $500 to $3,000 /pc. It is faster, the charging speed is 12-80
miles/ hour.
Level 3 Charger: $5,000 – $50,000/pc, It charge the fastest with charging
60-100 miles in about 20 minutes.
(2)Installation Cost
Level 2 charger :about $500 – $1,500.
Level 3: $10,000 – $20,000 for extensive electrical upgrades or construction.
(3)Operational Costs
Electricity Cost: Typically $0.1 to $0.15 per kWh.
Level 2: $200 – $500 annually. If the ev charger is 22kw , the electricity cost for
charging is approximately $2.64 – $3.33/h.
Level 3 :above $3,500annually .Output power is usually between 50 kw – 350 kw.
Take 50 kw as example, the electricity cost for charging is about $6 -$7.50/h.
(4)Government Incentives
Federal Incentives: Up to 30% of installation cost, capped at $30,000.Diffrent
state,The incentive is vary .In order to get accurate subsidy information,
recommended to consult directly with your state’s energy office or government
department that specializes in handling such subsidies.
Cost Type | Level 2 Charger | Level 3 Charger |
Purchasing Cost | $500 – $3,000 | $5,000 – $50,000 |
Installation Cost | $500 – $1,500 | $10,000 – $20,000 |
Operation Cost | $200 – $500 | above $3,500 |
Total Cost (First Year) | $1,200 – $5,000 | above $18,500 |
Conclusion
Before choose commercial ev charger , please consider :Evaluate the expected
traffic and charging needs.If no economy limited ,for high traffic and charging
needs ,recommend level 3 ev charging . If low traffic and charging need ,
recommend level 2 charging .